- Sheikh Mohammed inaugurated DEWA's 250-megawatt pumped-storage hydroelectric plant in Hatta, built for AED 1.4 billion.
- The plant stores 1,500 megawatt-hours and runs on clean power from the Mohammed bin Rashid Al Maktoum Solar Park.
- DEWA says it is the first such facility in the GCC, with an estimated 80-year lifespan.
The latest:
A 250-megawatt pumped-storage hydroelectric plant went into operation in Hatta on 26 November, inaugurated by Sheikh Mohammed bin Rashid during a tour of development projects in the area. DEWA says the AED 1.4 billion facility is the first of its kind in the GCC. Saeed Mohammed Al Tayer briefed Sheikh Mohammed on the project, built under Hatta’s comprehensive development plan.
Details:
- The numbers: DEWA puts the plant’s generation capacity at 250 megawatts and its storage capacity at 1,500 megawatt-hours, with an estimated lifespan of 80 years. Total investment reached AED 1.4 billion, and the project recorded more than 22 million work hours.
- How it works: According to DEWA, the plant’s turbines use clean energy generated at the Mohammed bin Rashid Al Maktoum Solar Park to pump water from Hatta Dam to an upper dam. Electricity is generated as the water flows back down to Hatta Dam.
- The reservoirs: Hatta Dam has a storage capacity of 9 million cubic metres, while the upper dam holds 5.3 million cubic metres, DEWA said. Sheikh Mohammed viewed the turbines in operation during the inauguration.
- The strategy link: Sheikh Mohammed commended DEWA’s projects as supporting the UAE Net Zero 2050 Strategy and the Dubai Clean Energy Strategy 2050, and pointed to the role of environmental conservation in sustainable development, according to the utility.
- The wider plan: The projects fall under the Hatta Master Development Plan, launched by Sheikh Mohammed in 2021 within the Dubai 2040 Urban Master Plan. He was briefed on implementation of Hatta Master Development Plan 2040, which targets an economic impact of roughly AED 1.2 billion by 2040.
- The directives: Sheikh Mohammed instructed relevant entities to align investment opportunities with Hatta’s development needs, widen private sector participation, diversify the local economy and improve services. No timeline was announced for those steps.
- Housing, phase two: The tour covered Makan 2, an AED 500 million housing project by the Mohammed Bin Rashid Housing Establishment comprising 213 villas. Sheikh Mohammed directed that allocation procedures be expedited, with units scheduled for allocation by the end of December 2026.
- Housing, phase one: He also visited Makan 1, a AED 600 million project of 344 villas completed three years ago. Together the two schemes account for 557 villas and AED 1.1 billion in stated investment.
Background:
Pumped storage holds energy by moving water uphill when power is available and releasing it downhill to drive turbines when it is needed. DEWA says the Hatta plant draws that pumping power from the Mohammed bin Rashid Al Maktoum Solar Park, tying the storage directly to solar output.
Between the lines:
The plant’s value sits in timing rather than volume: 1,500 megawatt-hours of storage gives Dubai a way to hold solar generation from the Mohammed bin Rashid Al Maktoum Solar Park and release it after sunset. That matches the framing Sheikh Mohammed used, linking DEWA’s work to the Dubai Clean Energy Strategy 2050. The AED 1.2 billion economic target for Hatta by 2040 shows the utility project is also an economic development play.